Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Prairie State Generating
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
—MW
CO₂ concentration
11.4%vol%
▸Direct Field Costs$1.89B
Report did not provide a further cost breakdown.
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B
Technology Centre Mongstad
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
▸Direct Field Costs$1.65B
Coal & Sorbent Handling Equipment Cost—
Coal & Sorbent Prep & Feed Equipment Cost—
Feedwater & Misc. Balance of Plant Systems Equipment Cost—
Pulverized coal-fired boiler Equipment Cost—
Flue Gas Cleanup Equipment Cost—
CO2 Capture System Equipment Cost—
CO2 Compression and Purification Equipment—
HRSG, Ducting & Stack Equipment Cost—
Steam Turbine Generator Equipment Cost—
Cooling Water System Equipment Cost—
Ash/Spent Sorbent Handling System Equipment Cost—
Accessory Electric Plant Equipment Cost—
Instrumentation & Control Equipment Cost—
Improvements to Site Equipment Cost—
Materials Cost—
Labor—
▸Indirect Field Costs$187.0M
Engineering—
▸Contingency & Escalation$418.3M
Project Contingency—
Process Contingency—
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$507.6M
Financing Cost—
Pre-production Cost—
Inventory Capital—
Other's owners cost—
Total Capex$3.19B
Southern Company / Plant Daniel
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
—
▸Direct Field Costs$515.2M
Engineering-Procured Materials—
Construction – Including Labor, Materials, and Contracted Equipment—
▸Indirect Field Costs$56.6M
Project Management—
Engineering – Including Construction and Startup Support—
▸Contingency & Escalation$126.3M
Contingency—
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$54.1M
Front End Planning—
Startup—
Other's owners cost—
Total Capex$752.2M