Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Prairie State Generating

CoalFEED· University of Illinois· 2022-09-03Project page ↗Cost report ↗
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
11.4%vol%
Direct Field Costs$1.89B
Report did not provide a further cost breakdown.
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Direct Field Costs$1.65B
Coal & Sorbent Handling Equipment Cost
Coal & Sorbent Prep & Feed Equipment Cost
Feedwater & Misc. Balance of Plant Systems Equipment Cost
Pulverized coal-fired boiler Equipment Cost
Flue Gas Cleanup Equipment Cost
CO2 Capture System Equipment Cost
CO2 Compression and Purification Equipment
HRSG, Ducting & Stack Equipment Cost
Steam Turbine Generator Equipment Cost
Cooling Water System Equipment Cost
Ash/Spent Sorbent Handling System Equipment Cost
Accessory Electric Plant Equipment Cost
Instrumentation & Control Equipment Cost
Improvements to Site Equipment Cost
Materials Cost
Labor
Indirect Field Costs$187.0M
Engineering
Contingency & Escalation$418.3M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$507.6M
Financing Cost
Pre-production Cost
Inventory Capital
Other's owners cost
Total Capex$3.19B

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Foundations
Civil and Structural
Piping and Ducting
NGCC Base Modifications Equipment Cost
Exhaust Gas Recirculation System Equipment Cost
Gas Turbine Modifications Equipment Cost
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Cost
CO2 Compression Equipment
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Cost
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC
Initial fill of CCS inventory (Solvent and Activated Carbon)'
Labor
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B