Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Southern Company / Plant Daniel
COโ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
โ
Parasitic load
79MW
COโ concentration
โ
โธDirect Field Costs$515.2M
Engineering-Procured Materialsโ
Construction โ Including Labor, Materials, and Contracted Equipmentโ
โธIndirect Field Costs$56.6M
Project Managementโ
Engineering โ Including Construction and Startup Supportโ
โธContingency & Escalation$126.3M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$54.1M
Front End Planningโ
Startupโ
Other's owners costโ
Total Capex$752.2M
Prairie State Generating
COโ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
โMW
COโ concentration
11.4%vol%
โธDirect Field Costs$1.89B
Report did not provide a further cost breakdown.
โธIndirect Field Costsโ
Report did not provide a further cost breakdown.
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B
Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln
Pulp and Paperpre-FEEDยท VTT Technical Research Centre of Finlandยท 2016-12-01Project page โCost report โ
COโ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
COโ concentration
15.7%mol%
โธDirect Field Costs$385.8M
Recovery Boiler: booster fan and ductworkโ
Lime Kiln: booster fan and ductworkโ
Multi-fuel boiler: booster fan and ductworkโ
Steam turbine island modificationsโ
Auxiliary boiler modificationsโ
Waste waster treatmentโ
Common flue gas stackโ
Direct Contact Coolerโ
Amine absorber sectionโ
Amine circulation systemโ
Stripper sectionโ
CO2 Compression and dehydrationโ
Auxiliariesโ
Other direct material costโ
Constructionโ
EPC and other costsโ
โธIndirect Field Costsโ
Report did not provide a further cost breakdown.
โธContingency & Escalation$38.6M
Contingencyโ
โธInterest During Construction$62.9M
Report did not provide a further cost breakdown.
โธOwners Cost$45.5M
Report did not provide a further cost breakdown.
Total Capex$532.7M