Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Daniel

Natural GasFEED· Southern Company· 2022-11-30Project page ↗Cost report ↗
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
79MW
CO₂ concentration
Direct Field Costs$515.2M
Engineering-Procured Materials
Construction – Including Labor, Materials, and Contracted Equipment
Indirect Field Costs$56.6M
Project Management
Engineering – Including Construction and Startup Support
Contingency & Escalation$126.3M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$54.1M
Front End Planning
Startup
Other's owners cost
Total Capex$752.2M

Finnish Market Pulp Mill / Capture of CO2 in both Kraft Boiler & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,675,922t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
26.9MW
CO₂ concentration
15.5%mol%
Direct Field Costs$292.9M
Recovery Boiler: booster fan and ductwork
Lime Kiln: booster fan and ductwork
Multi-fuel boiler: booster fan and ductwork
Steam turbine island modifications
Auxiliary boiler modifications
Waste waster treatment
Common flue gas stack
Direct Contact Cooler
Amine absorber section
Amine circulation system
Stripper section
CO2 Compression and dehydration
Auxiliaries
Other direct material cost
Construction
EPC and other costs
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$29.3M
Contingency
Interest During Construction$47.6M
Report did not provide a further cost breakdown.
Owners Cost$33.0M
Report did not provide a further cost breakdown.
Total Capex$402.8M

Southern Company / Plant Barry

All· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.7M
Dehydration
CO2 Compression Equipment
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.7M