Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Southern Company / Plant Barry
COโ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
COโ concentration
6.7%mol%
โธDirect Field Costs$1.10B
Foundationsโ
Civil and Structuralโ
Piping and Ductingโ
NGCC Base Modifications Equipment Costโ
Exhaust Gas Recirculation System Equipment Costโ
Gas Turbine Modifications Equipment Costโ
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Costโ
CO2 Compression Equipmentโ
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Costโ
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCCโ
Initial fill of CCS inventory (Solvent and Activated Carbon)'โ
Laborโ
โธIndirect Field Costsโ
Report did not provide a further cost breakdown.
โธContingency & Escalation$192.4M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$1.29B
CEMEX / Balcones Cement Plant
COโ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
โMW
COโ concentration
12.8%mol%
โธDirect Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumpsโ
Piping materials, ductwork, racksโ
Civil materials, concrete, site materialsโ
Structural steel materialsโ
Electrical materials and equipmentโ
Instruments and automation hardwareโ
Insulation materialsโ
Paint and coatingsโ
Freight, heavy lift, haulingโ
All field installation laborโ
โธIndirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overheadโ
EPC engineering and detailed designโ
โธContingency & Escalation$145.5M
Contingencyโ
Escalationโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$23.6M
Owner's costโ
Total Capex$849.3M
CLECO / Brame Energy Center Madison 3 Unit
CoalFEEDยท Cleco Powerยท 2025-03-25
COโ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
โMW
COโ concentration
14.1%vol%
โธDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
โธIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
โธContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$1.30B