Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Southern Company / Plant Barry

Natural GasFEEDยท GE Gas Powerยท 2024-08-06Project page โ†—Cost report โ†—
COโ‚‚ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
COโ‚‚ concentration
6.7%mol%
โ–ธDirect Field Costs$1.10B
Foundationsโ€”
Civil and Structuralโ€”
Piping and Ductingโ€”
NGCC Base Modifications Equipment Costโ€”
Exhaust Gas Recirculation System Equipment Costโ€”
Gas Turbine Modifications Equipment Costโ€”
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Costโ€”
CO2 Compression Equipmentโ€”
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Costโ€”
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCCโ€”
Initial fill of CCS inventory (Solvent and Activated Carbon)'โ€”
Laborโ€”
โ–ธIndirect Field Costsโ€”
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$192.4M
Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Costโ€”
Report did not provide a further cost breakdown.
Total Capex$1.29B

CEMEX / Balcones Cement Plant

ยท Sargent and Lundyยท 2026-01-01Cost report โ†—
COโ‚‚ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
12.8%mol%
โ–ธDirect Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumpsโ€”
Piping materials, ductwork, racksโ€”
Civil materials, concrete, site materialsโ€”
Structural steel materialsโ€”
Electrical materials and equipmentโ€”
Instruments and automation hardwareโ€”
Insulation materialsโ€”
Paint and coatingsโ€”
Freight, heavy lift, haulingโ€”
All field installation laborโ€”
โ–ธIndirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overheadโ€”
EPC engineering and detailed designโ€”
โ–ธContingency & Escalation$145.5M
Contingencyโ€”
Escalationโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$23.6M
Owner's costโ€”
Total Capex$849.3M

CLECO / Brame Energy Center Madison 3 Unit

CoalFEEDยท Cleco Powerยท 2025-03-25
COโ‚‚ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
14.1%vol%
โ–ธDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
โ–ธIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Costโ€”
Report did not provide a further cost breakdown.
Total Capex$1.30B