Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
▸Direct Field Costs$71.7M
Major Equipment—
Module Shop Fabrication—
Site Installation—
▸Indirect Field Costs$6.7M
Engineering—
Project Management—
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$78.4M
CEMEX / Balcones Cement Plant
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
—MW
CO₂ concentration
12.8%mol%
▸Direct Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumps—
Piping materials, ductwork, racks—
Civil materials, concrete, site materials—
Structural steel materials—
Electrical materials and equipment—
Instruments and automation hardware—
Insulation materials—
Paint and coatings—
Freight, heavy lift, hauling—
All field installation labor—
▸Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead—
EPC engineering and detailed design—
▸Contingency & Escalation$145.5M
Contingency—
Escalation—
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$23.6M
Owner's cost—
Total Capex$849.3M
Technology Centre Mongstad
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
▸Direct Field Costs$1.65B
Coal & Sorbent Handling Equipment Cost—
Coal & Sorbent Prep & Feed Equipment Cost—
Feedwater & Misc. Balance of Plant Systems Equipment Cost—
Pulverized coal-fired boiler Equipment Cost—
Flue Gas Cleanup Equipment Cost—
CO2 Capture System Equipment Cost—
CO2 Compression and Purification Equipment—
HRSG, Ducting & Stack Equipment Cost—
Steam Turbine Generator Equipment Cost—
Cooling Water System Equipment Cost—
Ash/Spent Sorbent Handling System Equipment Cost—
Accessory Electric Plant Equipment Cost—
Instrumentation & Control Equipment Cost—
Improvements to Site Equipment Cost—
Materials Cost—
Labor—
▸Indirect Field Costs$187.0M
Engineering—
▸Contingency & Escalation$418.3M
Project Contingency—
Process Contingency—
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$507.6M
Financing Cost—
Pre-production Cost—
Inventory Capital—
Other's owners cost—
Total Capex$3.19B