Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Scottish Power / Longannet Power Station

Natural GasFEEDยท ScottishPowerยท 2011-04-01Project page โ†—
COโ‚‚ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
โ€”MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$509.8M
Steam and Power Supplyโ€”
Carbon Capture Processโ€”
Compression and Conditioningโ€”
Balance of Plant and Utilitiesโ€”
โ–ธIndirect Field Costsโ€”
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$98.5M
Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M

Gerald Gentleman Station

CoalFEEDยท ION Clean Energyยท 2023-03-01Project page โ†—Cost report โ†—
COโ‚‚ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$2.17B
Switchyardโ€”
Auxiliary power and fansโ€”
Absorberโ€”
Common facilitiesโ€”
Carbon Capture Plantโ€”
โ–ธIndirect Field Costsโ€”
Report did not provide a further cost breakdown.
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Costโ€”
Report did not provide a further cost breakdown.
Total Capex$2.17B

Rayburn Energy Station / Sherman Power Plant

Natural GasFEEDยท Bechtelยท 2022-03-01Project page โ†—Cost report โ†—
COโ‚‚ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ‚‚ concentration
6.0%mol%
โ–ธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ€”
CO2 absorptionโ€”
Civil structural workโ€”
General utility systemโ€”
CO2 Compression Equipmentโ€”
Flue Gas Conditioningโ€”
Solvent regenerationโ€”
Stack connection and modificationโ€”
โ–ธIndirect Field Costs$59.1M
Construction preliminariesโ€”
Engineeringโ€”
Mechanical completion, commissioning and testingโ€”
Trainingโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โ–ธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M