Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Scottish Power / Longannet Power Station

Natural GasFEED· ScottishPower· 2011-04-01Project page ↗
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Direct Field Costs$509.8M
Steam and Power Supply
Carbon Capture Process
Compression and Conditioning
Balance of Plant and Utilities
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$98.5M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M

Southern Company / Plant Barry

All· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$91.8M
Dehydration
CO2 Compression Equipment
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$91.8M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft & Multi-boilers

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
Direct Field Costs$366.5M
Recovery Boiler: booster fan and ductwork
Lime Kiln: booster fan and ductwork
Multi-fuel boiler: booster fan and ductwork
Steam turbine island modifications
Auxiliary boiler modifications
Waste waster treatment
Common flue gas stack
Direct Contact Cooler
Amine absorber section
Amine circulation system
Stripper section
CO2 Compression and dehydration
Auxiliaries
Other direct material cost
Construction
EPC and other costs
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$36.7M
Contingency
Interest During Construction$59.7M
Report did not provide a further cost breakdown.
Owners Cost$43.2M
Report did not provide a further cost breakdown.
Total Capex$506.0M