Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports β€” tab selection applies to every column.

CLECO / Brame Energy Center Madison 3 Unit

CoalFEEDΒ· Cleco PowerΒ· 2025-03-25
COβ‚‚ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
β€”MW
COβ‚‚ concentration
14.1%vol%
β–ΈDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
β–ΈIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
β–ΈContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$1.30B

Milton R. Young Power Plant

CoalFEEDΒ· Minnkota Power CooperativeΒ· 2023-02-20Project page β†—Cost report β†—
COβ‚‚ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
COβ‚‚ concentration
8.6%vol%
β–ΈDirect Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)β€”
Earthwork Associated with Carbon Captureβ€”
Water Supply and Treatmentβ€”
Wastewaterβ€”
Drainageβ€”
Power Supplyβ€”
Controls & Internetβ€”
Owner Facilitiesβ€”
Impurity Removal and CO2 conditioningβ€”
Enclosures & Buildingsβ€”
Carbon Capture Plantβ€”
β–ΈIndirect Field Costs$61.5M
Project Managementβ€”
Limited Notice to Proceedβ€”
Servicesβ€”
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)β€”
β–ΈContingency & Escalation$470.0M
Owner's Cost Contingencyβ€”
EPC Contingencyβ€”
Escalationβ€”
Regional Adjustment for Laborβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$71.2M
Spare Partsβ€”
License feeβ€”
Insuranceβ€”
Startupβ€”
Miscellaneousβ€”
Total Capex$1.95B

Southern Company / Plant Barry

AllΒ· TrimericΒ· 2020-02-01Project page β†—Cost report β†—
COβ‚‚ captured
4,200,000t/yr
Capture efficiency
β€”
Utilization
95.0%
Parasitic load
β€”MW
COβ‚‚ concentration
99.0%vol%
β–ΈDirect Field Costs$154.5M
Dehydrationβ€”
CO2 Compression Equipmentβ€”
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingenciesβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalationβ€”
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$154.5M