Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports β tab selection applies to every column.
CLECO / Brame Energy Center Madison 3 Unit
CoalFEEDΒ· Cleco PowerΒ· 2025-03-25
COβ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
βMW
COβ concentration
14.1%vol%
βΈDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
βΈIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
βΈContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Costβ
Report did not provide a further cost breakdown.
Total Capex$1.30B
Milton R. Young Power Plant
COβ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
COβ concentration
8.6%vol%
βΈDirect Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)β
Earthwork Associated with Carbon Captureβ
Water Supply and Treatmentβ
Wastewaterβ
Drainageβ
Power Supplyβ
Controls & Internetβ
Owner Facilitiesβ
Impurity Removal and CO2 conditioningβ
Enclosures & Buildingsβ
Carbon Capture Plantβ
βΈIndirect Field Costs$61.5M
Project Managementβ
Limited Notice to Proceedβ
Servicesβ
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)β
βΈContingency & Escalation$470.0M
Owner's Cost Contingencyβ
EPC Contingencyβ
Escalationβ
Regional Adjustment for Laborβ
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Cost$71.2M
Spare Partsβ
License feeβ
Insuranceβ
Startupβ
Miscellaneousβ
Total Capex$1.95B
Southern Company / Plant Barry
COβ captured
4,200,000t/yr
Capture efficiency
β
Utilization
95.0%
Parasitic load
βMW
COβ concentration
99.0%vol%
βΈDirect Field Costs$153.0M
Dehydrationβ
CO2 Compression Equipmentβ
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractorsβ fees, and process and project contingenciesβ
βΈIndirect Field Costsβ
Report did not provide a further cost breakdown.
βΈContingency & Escalationβ
Report did not provide a further cost breakdown.
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Costβ
Report did not provide a further cost breakdown.
Total Capex$153.0M