Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

CLECO / Brame Energy Center Madison 3 Unit

CoalFEEDยท Cleco Powerยท 2025-03-25
COโ‚‚ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
14.1%vol%
โ–ธDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
โ–ธIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Costโ€”
Report did not provide a further cost breakdown.
Total Capex$1.30B

Milton R. Young Power Plant

CoalFEEDยท Minnkota Power Cooperativeยท 2023-02-20Project page โ†—Cost report โ†—
COโ‚‚ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
COโ‚‚ concentration
8.6%vol%
โ–ธDirect Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)โ€”
Earthwork Associated with Carbon Captureโ€”
Water Supply and Treatmentโ€”
Wastewaterโ€”
Drainageโ€”
Power Supplyโ€”
Controls & Internetโ€”
Owner Facilitiesโ€”
Impurity Removal and CO2 conditioningโ€”
Enclosures & Buildingsโ€”
Carbon Capture Plantโ€”
โ–ธIndirect Field Costs$61.5M
Project Managementโ€”
Limited Notice to Proceedโ€”
Servicesโ€”
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)โ€”
โ–ธContingency & Escalation$470.0M
Owner's Cost Contingencyโ€”
EPC Contingencyโ€”
Escalationโ€”
Regional Adjustment for Laborโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$71.2M
Spare Partsโ€”
License feeโ€”
Insuranceโ€”
Startupโ€”
Miscellaneousโ€”
Total Capex$1.95B

Holcim / Portland Cement Plant

Cementpre-FEEDยท Electricoreยท 2023-01-31Project page โ†—Cost report โ†—
COโ‚‚ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
76MW
COโ‚‚ concentration
10.1%vol%
โ–ธDirect Field Costs$292.8M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expenseโ€”
Purchased Equipment Costsโ€”
โ–ธIndirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingenciesโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costsโ€”
Total Capex$411.5M