Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CRC / Elk Hills Power Plant

Natural GasFEED· Electric Power Research Institute (EPRI)· 2020-09-01Project page ↗Cost report ↗
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
Direct Field Costs$444.7M
Earthwork & Civil
Concrete
Structural Steel
Capture Plant Equipment
Utilities Equipment
CO2 Compression Equipment
Piping
Electrical and Control Systems
Scaffolding, Painting, Insulation
Modularization
Procurement, Taxes & Duties
Pre-commisioning and Startup
Indirect Field Costs$206.3M
Indirect Field Costs
Home Office
EPC Fees
Contingency & Escalation$96.0M
Escalation
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Multi-fuel Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
270,658t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
4.4MW
CO₂ concentration
16.8%mol%
Direct Field Costs$83.0M
Recovery Boiler: booster fan and ductwork
Lime Kiln: booster fan and ductwork
Multi-fuel boiler: booster fan and ductwork
Steam turbine island modifications
Auxiliary boiler modifications
Waste waster treatment
Common flue gas stack
Direct Contact Cooler
Amine absorber section
Amine circulation system
Stripper section
CO2 Compression and dehydration
Auxiliaries
Other direct material cost
Construction
EPC and other costs
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$8.3M
Contingency
Interest During Construction$13.5M
Report did not provide a further cost breakdown.
Owners Cost$9.2M
Report did not provide a further cost breakdown.
Total Capex$114.0M

Finnish Market Pulp Mill / Capture of CO2 in both Kraft & Multi-boilers

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
Direct Field Costs$309.2M
Recovery Boiler: booster fan and ductwork
Lime Kiln: booster fan and ductwork
Multi-fuel boiler: booster fan and ductwork
Steam turbine island modifications
Auxiliary boiler modifications
Waste waster treatment
Common flue gas stack
Direct Contact Cooler
Amine absorber section
Amine circulation system
Stripper section
CO2 Compression and dehydration
Auxiliaries
Other direct material cost
Construction
EPC and other costs
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$30.9M
Contingency
Interest During Construction$50.2M
Report did not provide a further cost breakdown.
Owners Cost$34.9M
Report did not provide a further cost breakdown.
Total Capex$425.2M