Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Peterhead Power Station (Aberdeenshire)
COโ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
โ
Parasitic load
โMW
COโ concentration
โ
โธDirect Field Costs$331.4M
Electrical and Instrumentation / E&Iโ
Water Systemโ
CO2 Compression Equipmentโ
Constructionโ
Carbon Capture Plantโ
โธIndirect Field Costs$89.7M
Indirect Field Costsโ
Engineeringโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M
Southern Company / Plant Daniel
COโ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
โ
Parasitic load
79MW
COโ concentration
โ
โธDirect Field Costs$515.2M
Engineering-Procured Materialsโ
Construction โ Including Labor, Materials, and Contracted Equipmentโ
โธIndirect Field Costs$56.6M
Project Managementโ
Engineering โ Including Construction and Startup Supportโ
โธContingency & Escalation$126.3M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$54.1M
Front End Planningโ
Startupโ
Other's owners costโ
Total Capex$752.2M
Southern Company / Plant Barry
COโ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
COโ concentration
6.7%mol%
โธDirect Field Costs$1.10B
Foundationsโ
Civil and Structuralโ
Piping and Ductingโ
NGCC Base Modifications Equipment Costโ
Exhaust Gas Recirculation System Equipment Costโ
Gas Turbine Modifications Equipment Costโ
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Costโ
CO2 Compression Equipmentโ
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Costโ
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCCโ
Initial fill of CCS inventory (Solvent and Activated Carbon)'โ
Laborโ
โธIndirect Field Costsโ
Report did not provide a further cost breakdown.
โธContingency & Escalation$192.4M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$1.29B