Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Peterhead Power Station (Aberdeenshire)

Natural GasFEEDยท Shellยท โ€”Project page โ†—Cost report โ†—
COโ‚‚ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
โ€”MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$331.4M
Electrical and Instrumentation / E&Iโ€”
Water Systemโ€”
CO2 Compression Equipmentโ€”
Constructionโ€”
Carbon Capture Plantโ€”
โ–ธIndirect Field Costs$89.7M
Indirect Field Costsโ€”
Engineeringโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M

Rayburn Energy Station / Sherman Power Plant

Natural GasFEEDยท Bechtelยท 2022-03-01Project page โ†—Cost report โ†—
COโ‚‚ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ‚‚ concentration
6.0%mol%
โ–ธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ€”
CO2 absorptionโ€”
Civil structural workโ€”
General utility systemโ€”
CO2 Compression Equipmentโ€”
Flue Gas Conditioningโ€”
Solvent regenerationโ€”
Stack connection and modificationโ€”
โ–ธIndirect Field Costs$59.1M
Construction preliminariesโ€”
Engineeringโ€”
Mechanical completion, commissioning and testingโ€”
Trainingโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โ–ธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M

Southern Company / Plant Daniel

Natural GasFEEDยท Southern Companyยท 2022-11-30Project page โ†—Cost report โ†—
COโ‚‚ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
79MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$515.2M
Engineering-Procured Materialsโ€”
Construction โ€“ Including Labor, Materials, and Contracted Equipmentโ€”
โ–ธIndirect Field Costs$56.6M
Project Managementโ€”
Engineering โ€“ Including Construction and Startup Supportโ€”
โ–ธContingency & Escalation$126.3M
Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$54.1M
Front End Planningโ€”
Startupโ€”
Other's owners costโ€”
Total Capex$752.2M