Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Peterhead Power Station (Aberdeenshire)
COโ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
โ
Parasitic load
โMW
COโ concentration
โ
โธDirect Field Costs$331.4M
Electrical and Instrumentation / E&Iโ
Water Systemโ
CO2 Compression Equipmentโ
Constructionโ
Carbon Capture Plantโ
โธIndirect Field Costs$89.7M
Indirect Field Costsโ
Engineeringโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M
Rayburn Energy Station / Sherman Power Plant
COโ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ concentration
6.0%mol%
โธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ
CO2 absorptionโ
Civil structural workโ
General utility systemโ
CO2 Compression Equipmentโ
Flue Gas Conditioningโ
Solvent regenerationโ
Stack connection and modificationโ
โธIndirect Field Costs$59.1M
Construction preliminariesโ
Engineeringโ
Mechanical completion, commissioning and testingโ
Trainingโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
Southern Company / Plant Daniel
COโ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
โ
Parasitic load
79MW
COโ concentration
โ
โธDirect Field Costs$515.2M
Engineering-Procured Materialsโ
Construction โ Including Labor, Materials, and Contracted Equipmentโ
โธIndirect Field Costs$56.6M
Project Managementโ
Engineering โ Including Construction and Startup Supportโ
โธContingency & Escalation$126.3M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$54.1M
Front End Planningโ
Startupโ
Other's owners costโ
Total Capex$752.2M