Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports β€” tab selection applies to every column.

Southern Company / Plant Barry

AllΒ· TrimericΒ· 2020-02-01Project page β†—Cost report β†—
COβ‚‚ captured
4,200,000t/yr
Capture efficiency
β€”
Utilization
95.0%
Parasitic load
β€”MW
COβ‚‚ concentration
99.0%vol%
β–ΈDirect Field Costs$154.5M
Dehydrationβ€”
CO2 Compression Equipmentβ€”
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingenciesβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalationβ€”
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$154.5M

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEEDΒ· Devon EnergyΒ· 2011-11-01Project page β†—Cost report β†—
COβ‚‚ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
β€”MW
COβ‚‚ concentration
8.6%mol%
β–ΈDirect Field Costs$71.7M
Major Equipmentβ€”
Module Shop Fabricationβ€”
Site Installationβ€”
β–ΈIndirect Field Costs$6.7M
Engineeringβ€”
Project Managementβ€”
β–ΈContingency & Escalationβ€”
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$78.4M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEEDΒ· VTT Technical Research Centre of FinlandΒ· 2016-12-01Project page β†—Cost report β†—
COβ‚‚ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
COβ‚‚ concentration
15.7%mol%
β–ΈDirect Field Costs$385.8M
Recovery Boiler: booster fan and ductworkβ€”
Lime Kiln: booster fan and ductworkβ€”
Multi-fuel boiler: booster fan and ductworkβ€”
Steam turbine island modificationsβ€”
Auxiliary boiler modificationsβ€”
Waste waster treatmentβ€”
Common flue gas stackβ€”
Direct Contact Coolerβ€”
Amine absorber sectionβ€”
Amine circulation systemβ€”
Stripper sectionβ€”
CO2 Compression and dehydrationβ€”
Auxiliariesβ€”
Other direct material costβ€”
Constructionβ€”
EPC and other costsβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalation$38.6M
Contingencyβ€”
β–ΈInterest During Construction$62.9M
Report did not provide a further cost breakdown.
β–ΈOwners Cost$45.5M
Report did not provide a further cost breakdown.
Total Capex$532.7M