Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports β tab selection applies to every column.
Southern Company / Plant Barry
COβ captured
4,200,000t/yr
Capture efficiency
β
Utilization
95.0%
Parasitic load
βMW
COβ concentration
99.0%vol%
βΈDirect Field Costs$153.0M
Dehydrationβ
CO2 Compression Equipmentβ
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractorsβ fees, and process and project contingenciesβ
βΈIndirect Field Costsβ
Report did not provide a further cost breakdown.
βΈContingency & Escalationβ
Report did not provide a further cost breakdown.
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Costβ
Report did not provide a further cost breakdown.
Total Capex$153.0M
Cleveland Cliffs / Burns Harbor
COβ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
β
Parasitic load
79MW
COβ concentration
21.9%vol%
βΈDirect Field Costs$445.8M
Blast Furance Gas Processing Equipment Costβ
Carbon Capture Island Equipment Costβ
Steam and Power System Equipment Costβ
Material Costβ
Laborβ
βΈIndirect Field Costs$66.9M
EPC Feesβ
βΈContingency & Escalation$67.5M
Contingencyβ
βΈInterest During Construction$74.5M
Report did not provide a further cost breakdown.
βΈOwners Cost$121.4M
Financing Costβ
Pre-production Costβ
Inventory Capitalβ
Other's owners costβ
Total Capex$776.1M
Calpine / Deer Park Energy Center
COβ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
COβ concentration
5.2%vol%
βΈDirect Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systemsβ
Combustion Turbine & Accessoriesβ
HRSG, Ductwork, & Stackβ
Steam Turbine & Accessoriesβ
Cooling Water Systemβ
Accessory Electric Plantβ
Instrumentation & Controlβ
Improvements to Siteβ
CO2 Capture Systemβ
Material Costβ
Direct Laborβ
βΈIndirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Feeβ
βΈContingency & Escalation$76.7M
Project Contingencyβ
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Cost$19.9M
Pre-production Costβ
Inventory Capitalβ
Total Capex$595.5M