Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports β€” tab selection applies to every column.

Southern Company / Plant Barry

AllΒ· TrimericΒ· 2020-02-01Project page β†—Cost report β†—
COβ‚‚ captured
4,200,000t/yr
Capture efficiency
β€”
Utilization
95.0%
Parasitic load
β€”MW
COβ‚‚ concentration
99.0%vol%
β–ΈDirect Field Costs$153.0M
Dehydrationβ€”
CO2 Compression Equipmentβ€”
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingenciesβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalationβ€”
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$153.0M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEEDΒ· Dastur InternationalΒ· 2023-03-01Project page β†—Cost report β†—
COβ‚‚ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
β€”
Parasitic load
79MW
COβ‚‚ concentration
21.9%vol%
β–ΈDirect Field Costs$445.8M
Blast Furance Gas Processing Equipment Costβ€”
Carbon Capture Island Equipment Costβ€”
Steam and Power System Equipment Costβ€”
Material Costβ€”
Laborβ€”
β–ΈIndirect Field Costs$66.9M
EPC Feesβ€”
β–ΈContingency & Escalation$67.5M
Contingencyβ€”
β–ΈInterest During Construction$74.5M
Report did not provide a further cost breakdown.
β–ΈOwners Cost$121.4M
Financing Costβ€”
Pre-production Costβ€”
Inventory Capitalβ€”
Other's owners costβ€”
Total Capex$776.1M

Calpine / Deer Park Energy Center

Natural GasFEEDΒ· CalpineΒ· 2023-05-03Project page β†—Cost report β†—
COβ‚‚ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
COβ‚‚ concentration
5.2%vol%
β–ΈDirect Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systemsβ€”
Combustion Turbine & Accessoriesβ€”
HRSG, Ductwork, & Stackβ€”
Steam Turbine & Accessoriesβ€”
Cooling Water Systemβ€”
Accessory Electric Plantβ€”
Instrumentation & Controlβ€”
Improvements to Siteβ€”
CO2 Capture Systemβ€”
Material Costβ€”
Direct Laborβ€”
β–ΈIndirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Feeβ€”
β–ΈContingency & Escalation$76.7M
Project Contingencyβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$19.9M
Pre-production Costβ€”
Inventory Capitalβ€”
Total Capex$595.5M