Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

All· Trimeric· 2020-02-01Project page ↗Cost report ↗
COâ‚‚ captured
1,000,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
COâ‚‚ concentration
99.0%vol%
â–¸Direct Field Costs$35.7M
Dehydration—
CO2 Compression Equipment—
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies—
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$35.7M

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
COâ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
—MW
COâ‚‚ concentration
16.2%mol%
â–¸Direct Field Costs$489.9M
Materials Cost—
Construction—
â–¸Indirect Field Costs$37.5M
Engineering—
â–¸Contingency & Escalation$86.6M
Project Contingency—
Process Contingency—
▸Interest During Construction—
Report did not provide a further cost breakdown.
â–¸Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Finnish Market Pulp Mill / Capture of CO2 in the Lime Kiln only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
COâ‚‚ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
COâ‚‚ concentration
27.6%mol%
â–¸Direct Field Costs$52.7M
Recovery Boiler: booster fan and ductwork—
Lime Kiln: booster fan and ductwork—
Multi-fuel boiler: booster fan and ductwork—
Steam turbine island modifications—
Auxiliary boiler modifications—
Waste waster treatment—
Common flue gas stack—
Direct Contact Cooler—
Amine absorber section—
Amine circulation system—
Stripper section—
CO2 Compression and dehydration—
Auxiliaries—
Other direct material cost—
Construction—
EPC and other costs—
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
â–¸Contingency & Escalation$5.3M
Contingency—
â–¸Interest During Construction$8.6M
Report did not provide a further cost breakdown.
â–¸Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.4M