Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
CO2 Technology
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)
Earthwork Associated with Carbon Capture
Water Supply and Treatment
Wastewater
Drainage
Power Supply
Controls & Internet
Owner Facilities
Impurity Removal and CO2 conditioning
Enclosures & Buildings
Carbon Capture Plant
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B

Linde Hydrogen Plant

Hydrogenpre-FEED· Praxair· 2022-11-03Project page ↗Cost report ↗
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
MW
CO₂ concentration
18.3%mol%
Direct Field Costs$327.0M
Construction
Carbon Capture Plant
Indirect Field Costs$32.0M
Engineering
Contingency & Escalation$81.0M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$10.0M
Report did not provide a further cost breakdown.
Total Capex$481.5M