Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
CO2 Technology
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Direct Field Costs$489.9M
Materials Cost
Construction
Indirect Field Costs$37.5M
Engineering
Contingency & Escalation$86.6M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Foundations
Civil and Structural
Piping and Ducting
NGCC Base Modifications Equipment Cost
Exhaust Gas Recirculation System Equipment Cost
Gas Turbine Modifications Equipment Cost
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Cost
CO2 Compression Equipment
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Cost
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC
Initial fill of CCS inventory (Solvent and Activated Carbon)'
Labor
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B