Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Finnish Market Pulp Mill / Capture of CO2 in the Kraft Recovery Boiler only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,478,700t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
23.5MW
CO₂ concentration
14.7%mol%
Direct Field Costs$278.2M
Recovery Boiler Modifications: booster fan and ductwork
Lime Kiln Modifications: booster fan and ductwork
Multi-fuel boiler Modifications: booster fan and ductwork
Steam turbine island modifications
Auxiliary boiler modifications
Waste waster treatment modifications
Common flue gas stack
Direct Contact Cooler
Amine absorber section
Amine circulation system
Stripper section
CO2 Compression and dehydration
Auxiliaries
Other direct material cost
Construction
EPC and other costs
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$27.8M
Contingency
Interest During Construction$45.2M
Report did not provide a further cost breakdown.
Owners Cost$31.3M
Report did not provide a further cost breakdown.
Total Capex$382.6M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
79MW
CO₂ concentration
21.9%vol%
Direct Field Costs$445.8M
Blast Furance Gas Processing Equipment Cost
Carbon Capture Island Equipment Cost
Steam and Power System Equipment Cost
Material Cost
Labor
Indirect Field Costs$66.9M
EPC Fees
Contingency & Escalation$67.5M
Contingency
Interest During Construction$74.5M
Report did not provide a further cost breakdown.
Owners Cost$121.4M
Financing Cost
Pre-production Cost
Inventory Capital
Other's owners cost
Total Capex$776.1M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2023-05-03Project page ↗Cost report ↗
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
Direct Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systems
Combustion Turbine & Accessories
HRSG, Ductwork, & Stack
Steam Turbine & Accessories
Cooling Water System
Accessory Electric Plant
Instrumentation & Control
Improvements to Site
CO2 Capture System
Material Cost
Direct Labor
Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$76.7M
Project Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$19.9M
Pre-production Cost
Inventory Capital
Total Capex$595.5M