Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Direct Field Costs$100.7M
Labor
Major Equipment
Site Improvements
Concrete
Structural Steel
Ductwork, Insulation, Piping
Instrumentation and Electrical
Painting
Freight
Design Allowance
Indirect Field Costs$60.9M
Indirect Labor
Indirect Materials
Engineering
Project Development (FEL 2 and 3)
Contingency & Escalation$48.3M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Major Equipment
Module Shop Fabrication
Site Installation
Indirect Field Costs$6.7M
Engineering
Project Management
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2023-05-03Project page ↗Cost report ↗
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
Direct Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systems
Combustion Turbine & Accessories
HRSG, Ductwork, & Stack
Steam Turbine & Accessories
Cooling Water System
Accessory Electric Plant
Instrumentation & Control
Improvements to Site
CO2 Capture System
Material Cost
Direct Labor
Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$76.7M
Project Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$19.9M
Pre-production Cost
Inventory Capital
Total Capex$595.5M