Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Linde / Port Arthur Facility
COโ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
โMW
COโ concentration
16.2%mol%
โธDirect Field Costs$489.9M
Materials Costโ
Constructionโ
โธIndirect Field Costs$37.5M
Engineeringโ
โธContingency & Escalation$86.6M
Project Contingencyโ
Process Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M
CEMEX / Balcones Cement Plant
COโ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
โMW
COโ concentration
12.8%mol%
โธDirect Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumpsโ
Piping materials, ductwork, racksโ
Civil materials, concrete, site materialsโ
Structural steel materialsโ
Electrical materials and equipmentโ
Instruments and automation hardwareโ
Insulation materialsโ
Paint and coatingsโ
Freight, heavy lift, haulingโ
All field installation laborโ
โธIndirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overheadโ
EPC engineering and detailed designโ
โธContingency & Escalation$145.5M
Contingencyโ
Escalationโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$23.6M
Owner's costโ
Total Capex$849.3M
Cleveland Cliffs / Burns Harbor
COโ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
โ
Parasitic load
79MW
COโ concentration
21.9%vol%
โธDirect Field Costs$445.8M
Blast Furance Gas Processing Equipment Costโ
Carbon Capture Island Equipment Costโ
Steam and Power System Equipment Costโ
Material Costโ
Laborโ
โธIndirect Field Costs$66.9M
EPC Feesโ
โธContingency & Escalation$67.5M
Contingencyโ
โธInterest During Construction$74.5M
Report did not provide a further cost breakdown.
โธOwners Cost$121.4M
Financing Costโ
Pre-production Costโ
Inventory Capitalโ
Other's owners costโ
Total Capex$776.1M