Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEEDยท Lindeยท 2023-12-04Project page โ†—Cost report โ†—
COโ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
16.2%mol%
โ–ธDirect Field Costs$489.9M
Materials Costโ€”
Constructionโ€”
โ–ธIndirect Field Costs$37.5M
Engineeringโ€”
โ–ธContingency & Escalation$86.6M
Project Contingencyโ€”
Process Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

CEMEX / Balcones Cement Plant

ยท Sargent and Lundyยท 2026-01-01Cost report โ†—
COโ‚‚ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
12.8%mol%
โ–ธDirect Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumpsโ€”
Piping materials, ductwork, racksโ€”
Civil materials, concrete, site materialsโ€”
Structural steel materialsโ€”
Electrical materials and equipmentโ€”
Instruments and automation hardwareโ€”
Insulation materialsโ€”
Paint and coatingsโ€”
Freight, heavy lift, haulingโ€”
All field installation laborโ€”
โ–ธIndirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overheadโ€”
EPC engineering and detailed designโ€”
โ–ธContingency & Escalation$145.5M
Contingencyโ€”
Escalationโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$23.6M
Owner's costโ€”
Total Capex$849.3M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEEDยท Dastur Internationalยท 2023-03-01Project page โ†—Cost report โ†—
COโ‚‚ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
โ€”
Parasitic load
79MW
COโ‚‚ concentration
21.9%vol%
โ–ธDirect Field Costs$445.8M
Blast Furance Gas Processing Equipment Costโ€”
Carbon Capture Island Equipment Costโ€”
Steam and Power System Equipment Costโ€”
Material Costโ€”
Laborโ€”
โ–ธIndirect Field Costs$66.9M
EPC Feesโ€”
โ–ธContingency & Escalation$67.5M
Contingencyโ€”
โ–ธInterest During Construction$74.5M
Report did not provide a further cost breakdown.
โ–ธOwners Cost$121.4M
Financing Costโ€”
Pre-production Costโ€”
Inventory Capitalโ€”
Other's owners costโ€”
Total Capex$776.1M