Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEEDยท Lindeยท 2023-12-04Project page โ†—Cost report โ†—
COโ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
16.2%mol%
โ–ธDirect Field Costs$489.9M
Materials Costโ€”
Constructionโ€”
โ–ธIndirect Field Costs$37.5M
Engineeringโ€”
โ–ธContingency & Escalation$86.6M
Project Contingencyโ€”
Process Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Scottish Power / Longannet Power Station

Natural GasFEEDยท ScottishPowerยท 2011-04-01Project page โ†—
COโ‚‚ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
โ€”MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$509.8M
Steam and Power Supplyโ€”
Carbon Capture Processโ€”
Compression and Conditioningโ€”
Balance of Plant and Utilitiesโ€”
โ–ธIndirect Field Costsโ€”
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$98.5M
Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M

Calpine / Deer Park Energy Center

Natural GasFEEDยท Calpineยท 2023-05-03Project page โ†—Cost report โ†—
COโ‚‚ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
COโ‚‚ concentration
5.2%vol%
โ–ธDirect Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systemsโ€”
Combustion Turbine & Accessoriesโ€”
HRSG, Ductwork, & Stackโ€”
Steam Turbine & Accessoriesโ€”
Cooling Water Systemโ€”
Accessory Electric Plantโ€”
Instrumentation & Controlโ€”
Improvements to Siteโ€”
CO2 Capture Systemโ€”
Material Costโ€”
Direct Laborโ€”
โ–ธIndirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Feeโ€”
โ–ธContingency & Escalation$76.7M
Project Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$19.9M
Pre-production Costโ€”
Inventory Capitalโ€”
Total Capex$595.5M