Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports β€” tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEEDΒ· LindeΒ· 2023-12-04Project page β†—Cost report β†—
COβ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
β€”MW
COβ‚‚ concentration
16.2%mol%
β–ΈDirect Field Costs$489.9M
Materials Costβ€”
Constructionβ€”
β–ΈIndirect Field Costs$37.5M
Engineeringβ€”
β–ΈContingency & Escalation$86.6M
Project Contingencyβ€”
Process Contingencyβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Scottish Power / Longannet Power Station

Natural GasFEEDΒ· ScottishPowerΒ· 2011-04-01Project page β†—
COβ‚‚ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
β€”
Parasitic load
β€”MW
COβ‚‚ concentration
β€”
β–ΈDirect Field Costs$509.8M
Steam and Power Supplyβ€”
Carbon Capture Processβ€”
Compression and Conditioningβ€”
Balance of Plant and Utilitiesβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalation$98.5M
Contingencyβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M

Mustang Station Power Plant

Natural GasFEEDΒ· University of Texas at AustinΒ· 2022-01-07Project page β†—Cost report β†—
COβ‚‚ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
COβ‚‚ concentration
3.8%vol%
β–ΈDirect Field Costs$384.1M
E&I Infrastructureβ€”
Solvent Pumping and Conditioningβ€”
Absorberβ€”
Wash Water Systemβ€”
Buildings & Facilitiesβ€”
Process Utilitiesβ€”
CO2 Compression Equipmentβ€”
Flue Gas Systemsβ€”
Solvent Reclaimingβ€”
Spare Parts, First Fills, Commodity Freightβ€”
Stripper, CO2 Conditioningβ€”
Steam Generationβ€”
Solvent Heat Exchangersβ€”
Solvent Storageβ€”
β–ΈIndirect Field Costs$209.7M
Indirect Field Costsβ€”
Contractor’s Profitβ€”
Engineeringβ€”
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)β€”
β–ΈContingency & Escalation$104.6M
Contingencyβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M