Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports β tab selection applies to every column.
Linde / Port Arthur Facility
COβ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
βMW
COβ concentration
16.2%mol%
βΈDirect Field Costs$489.9M
Materials Costβ
Constructionβ
βΈIndirect Field Costs$37.5M
Engineeringβ
βΈContingency & Escalation$86.6M
Project Contingencyβ
Process Contingencyβ
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M
Scottish Power / Longannet Power Station
COβ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
β
Parasitic load
βMW
COβ concentration
β
βΈDirect Field Costs$509.8M
Steam and Power Supplyβ
Carbon Capture Processβ
Compression and Conditioningβ
Balance of Plant and Utilitiesβ
βΈIndirect Field Costsβ
Report did not provide a further cost breakdown.
βΈContingency & Escalation$98.5M
Contingencyβ
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Cost$146.7M
Report did not provide a further cost breakdown.
Total Capex$755.0M
Mustang Station Power Plant
COβ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
COβ concentration
3.8%vol%
βΈDirect Field Costs$384.1M
E&I Infrastructureβ
Solvent Pumping and Conditioningβ
Absorberβ
Wash Water Systemβ
Buildings & Facilitiesβ
Process Utilitiesβ
CO2 Compression Equipmentβ
Flue Gas Systemsβ
Solvent Reclaimingβ
Spare Parts, First Fills, Commodity Freightβ
Stripper, CO2 Conditioningβ
Steam Generationβ
Solvent Heat Exchangersβ
Solvent Storageβ
βΈIndirect Field Costs$209.7M
Indirect Field Costsβ
Contractorβs Profitβ
Engineeringβ
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)β
βΈContingency & Escalation$104.6M
Contingencyβ
βΈInterest During Constructionβ
Report did not provide a further cost breakdown.
βΈOwners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M