Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEEDยท Lindeยท 2023-12-04Project page โ†—Cost report โ†—
COโ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
โ€”MW
COโ‚‚ concentration
16.2%mol%
โ–ธDirect Field Costs$489.9M
Materials Costโ€”
Constructionโ€”
โ–ธIndirect Field Costs$37.5M
Engineeringโ€”
โ–ธContingency & Escalation$86.6M
Project Contingencyโ€”
Process Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

CRC / Elk Hills Power Plant

Natural GasFEEDยท Electric Power Research Institute (EPRI)ยท 2020-09-01Project page โ†—Cost report โ†—
COโ‚‚ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
COโ‚‚ concentration
4.3%mol%
โ–ธDirect Field Costs$444.7M
Earthwork & Civilโ€”
Concreteโ€”
Structural Steelโ€”
Capture Plant Equipmentโ€”
Utilities Equipmentโ€”
CO2 Compression Equipmentโ€”
Pipingโ€”
Electrical and Control Systemsโ€”
Scaffolding, Painting, Insulationโ€”
Modularizationโ€”
Procurement, Taxes & Dutiesโ€”
Pre-commisioning and Startupโ€”
โ–ธIndirect Field Costs$206.3M
Indirect Field Costsโ€”
Home Officeโ€”
EPC Feesโ€”
โ–ธContingency & Escalation$96.0M
Escalationโ€”
Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M

Peterhead Power Station (Aberdeenshire)

Natural GasFEEDยท Shellยท โ€”Project page โ†—Cost report โ†—
COโ‚‚ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
โ€”MW
COโ‚‚ concentration
โ€”
โ–ธDirect Field Costs$331.4M
Electrical and Instrumentation / E&Iโ€”
Water Systemโ€”
CO2 Compression Equipmentโ€”
Constructionโ€”
Carbon Capture Plantโ€”
โ–ธIndirect Field Costs$89.7M
Indirect Field Costsโ€”
Engineeringโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$6.6M
Report did not provide a further cost breakdown.
Total Capex$427.7M