Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
COâ‚‚ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
—MW
COâ‚‚ concentration
16.2%mol%
â–¸Direct Field Costs$489.9M
Materials Cost—
Construction—
â–¸Indirect Field Costs$37.5M
Engineering—
â–¸Contingency & Escalation$86.6M
Project Contingency—
Process Contingency—
▸Interest During Construction—
Report did not provide a further cost breakdown.
â–¸Owners Cost$41.7M
Report did not provide a further cost breakdown.
Total Capex$701.6M

Southern Company / Plant Barry

All· Trimeric· 2020-02-01Project page ↗Cost report ↗
COâ‚‚ captured
2,400,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
COâ‚‚ concentration
99.0%vol%
â–¸Direct Field Costs$89.7M
Dehydration—
CO2 Compression Equipment—
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingencies—
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$89.7M

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
COâ‚‚ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
79MW
COâ‚‚ concentration
21.9%vol%
â–¸Direct Field Costs$445.8M
Blast Furance Gas Processing Equipment Cost—
Carbon Capture Island Equipment Cost—
Steam and Power System Equipment Cost—
Material Cost—
Labor—
â–¸Indirect Field Costs$66.9M
EPC Fees—
â–¸Contingency & Escalation$67.5M
Contingency—
â–¸Interest During Construction$74.5M
Report did not provide a further cost breakdown.
â–¸Owners Cost$121.4M
Financing Cost—
Pre-production Cost—
Inventory Capital—
Other's owners cost—
Total Capex$776.1M