Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expense
Purchased Equipment Costs
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs
Total Capex$411.5M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)
Earthwork Associated with Carbon Capture
Water Supply and Treatment
Wastewater
Drainage
Power Supply
Controls & Internet
Owner Facilities
Impurity Removal and CO2 conditioning
Enclosures & Buildings
Carbon Capture Plant
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
Foundations
Civil and Structural
Piping and Ducting
NGCC Base Modifications Equipment Cost
Exhaust Gas Recirculation System Equipment Cost
Gas Turbine Modifications Equipment Cost
CO2 Capture System (DCC, Absorber, Stripper and Reboiler) Equipment Cost
CO2 Compression Equipment
Cooling Water System (CCS Cooling Tower, Cooling Water Circulation Pumps and Heat Exchangers) Equipment Cost
CCS Balance of Plant (OSBL) Electrical, Civil, Mechanical Interfaces to NGCC
Initial fill of CCS inventory (Solvent and Activated Carbon)'
Labor
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B