Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Direct Field Costs$1.65B
Coal & Sorbent Handling Equipment Cost
Coal & Sorbent Prep & Feed Equipment Cost
Feedwater & Misc. Balance of Plant Systems Equipment Cost
Pulverized coal-fired boiler Equipment Cost
Flue Gas Cleanup Equipment Cost
CO2 Capture System Equipment Cost
CO2 Compression and Purification Equipment
HRSG, Ducting & Stack Equipment Cost
Steam Turbine Generator Equipment Cost
Cooling Water System Equipment Cost
Ash/Spent Sorbent Handling System Equipment Cost
Accessory Electric Plant Equipment Cost
Instrumentation & Control Equipment Cost
Improvements to Site Equipment Cost
Materials Cost
Labor
Indirect Field Costs$187.0M
Engineering
Contingency & Escalation$418.3M
Project Contingency
Process Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$507.6M
Financing Cost
Pre-production Cost
Inventory Capital
Other's owners cost
Total Capex$3.19B

(no name)

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Direct Field Costs$520.0M
Report did not provide a further cost breakdown.
Indirect Field Costs$160.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$293.2M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$973.6M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)
Earthwork Associated with Carbon Capture
Water Supply and Treatment
Wastewater
Drainage
Power Supply
Controls & Internet
Owner Facilities
Impurity Removal and CO2 conditioning
Enclosures & Buildings
Carbon Capture Plant
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B