Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports β€” tab selection applies to every column.

Technology Centre Mongstad

CoalLarge PilotΒ· Membrane Technology and Research (MTR)Β· 2023-08-15Project page β†—Cost report β†—
COβ‚‚ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
COβ‚‚ concentration
12.5%mol%
β–ΈDirect Field Costs$1.65B
Coal & Sorbent Handling Equipment Costβ€”
Coal & Sorbent Prep & Feed Equipment Costβ€”
Feedwater & Misc. Balance of Plant Systems Equipment Costβ€”
Pulverized coal-fired boiler Equipment Costβ€”
Flue Gas Cleanup Equipment Costβ€”
CO2 Capture System Equipment Costβ€”
CO2 Compression and Purification Equipmentβ€”
HRSG, Ducting & Stack Equipment Costβ€”
Steam Turbine Generator Equipment Costβ€”
Cooling Water System Equipment Costβ€”
Ash/Spent Sorbent Handling System Equipment Costβ€”
Accessory Electric Plant Equipment Costβ€”
Instrumentation & Control Equipment Costβ€”
Improvements to Site Equipment Costβ€”
Materials Costβ€”
Laborβ€”
β–ΈIndirect Field Costs$187.0M
Engineeringβ€”
β–ΈContingency & Escalation$418.3M
Project Contingencyβ€”
Process Contingencyβ€”
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Cost$507.6M
Financing Costβ€”
Pre-production Costβ€”
Inventory Capitalβ€”
Other's owners costβ€”
Total Capex$3.19B

(no name)

AmmoniaFEEDΒ· NutrienΒ· 2024-11-01Project page β†—
COβ‚‚ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
β€”
Parasitic load
β€”MW
COβ‚‚ concentration
7.0%mol%
β–ΈDirect Field Costs$1.09B
Report did not provide a further cost breakdown.
β–ΈIndirect Field Costs$337.8M
Report did not provide a further cost breakdown.
β–ΈContingency & Escalation$614.9M
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$2.04B

Southern Company / Plant Barry

AllΒ· TrimericΒ· 2020-02-01Project page β†—Cost report β†—
COβ‚‚ captured
4,200,000t/yr
Capture efficiency
β€”
Utilization
95.0%
Parasitic load
β€”MW
COβ‚‚ concentration
99.0%vol%
β–ΈDirect Field Costs$158.7M
Dehydrationβ€”
CO2 Compression Equipmentβ€”
Equipment installation, instrumentation and controls, piping, electrical, engineering, construction expenses, contractors’ fees, and process and project contingenciesβ€”
β–ΈIndirect Field Costsβ€”
Report did not provide a further cost breakdown.
β–ΈContingency & Escalationβ€”
Report did not provide a further cost breakdown.
β–ΈInterest During Constructionβ€”
Report did not provide a further cost breakdown.
β–ΈOwners Costβ€”
Report did not provide a further cost breakdown.
Total Capex$158.7M