Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports โ€” tab selection applies to every column.

Technology Centre Mongstad

CoalLarge Pilotยท Membrane Technology and Research (MTR)ยท 2023-08-15Project page โ†—Cost report โ†—
COโ‚‚ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
COโ‚‚ concentration
12.5%mol%
โ–ธDirect Field Costs$1.65B
Coal & Sorbent Handling Equipment Costโ€”
Coal & Sorbent Prep & Feed Equipment Costโ€”
Feedwater & Misc. Balance of Plant Systems Equipment Costโ€”
Pulverized coal-fired boiler Equipment Costโ€”
Flue Gas Cleanup Equipment Costโ€”
CO2 Capture System Equipment Costโ€”
CO2 Compression and Purification Equipmentโ€”
HRSG, Ducting & Stack Equipment Costโ€”
Steam Turbine Generator Equipment Costโ€”
Cooling Water System Equipment Costโ€”
Ash/Spent Sorbent Handling System Equipment Costโ€”
Accessory Electric Plant Equipment Costโ€”
Instrumentation & Control Equipment Costโ€”
Improvements to Site Equipment Costโ€”
Materials Costโ€”
Laborโ€”
โ–ธIndirect Field Costs$187.0M
Engineeringโ€”
โ–ธContingency & Escalation$418.3M
Project Contingencyโ€”
Process Contingencyโ€”
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$507.6M
Financing Costโ€”
Pre-production Costโ€”
Inventory Capitalโ€”
Other's owners costโ€”
Total Capex$3.19B

(no name)

AmmoniaFEEDยท Nutrienยท 2024-11-01Project page โ†—
COโ‚‚ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
โ€”
Parasitic load
โ€”MW
COโ‚‚ concentration
7.0%mol%
โ–ธDirect Field Costs$1.09B
Report did not provide a further cost breakdown.
โ–ธIndirect Field Costs$337.8M
Report did not provide a further cost breakdown.
โ–ธContingency & Escalation$614.9M
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Costโ€”
Report did not provide a further cost breakdown.
Total Capex$2.04B

Holcim / Portland Cement Plant

Cementpre-FEEDยท Electricoreยท 2023-01-31Project page โ†—Cost report โ†—
COโ‚‚ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
โ€”
Parasitic load
76MW
COโ‚‚ concentration
10.1%vol%
โ–ธDirect Field Costs$292.8M
Supporting Facilities, Materials, Bulks/Commodities, and Direct & Indirect Labor Expenseโ€”
Purchased Equipment Costsโ€”
โ–ธIndirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingenciesโ€”
โ–ธContingency & Escalationโ€”
Report did not provide a further cost breakdown.
โ–ธInterest During Constructionโ€”
Report did not provide a further cost breakdown.
โ–ธOwners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costsโ€”
Total Capex$411.5M