Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Direct Field Costs$900.4M
Instrumentaiton and Control
Feedwater & Misc. Balance of Plant Equipment & Systems
Accessory Electric Plant
Cooling Water System
Buldings & Structure
Improvements to Site
CO2 Compression Equipment
Flue Gas Cleanup
Ductwork and Stack
Labor
Carbon Capture Plant
Indirect Field Costs$517.7M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$250.5M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.0M
Financing Cost
Pre-production Cost
Inventory Capital
Total Capex$1.74B

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2023-05-03Project page ↗Cost report ↗
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
Direct Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systems
Combustion Turbine & Accessories
HRSG, Ductwork, & Stack
Steam Turbine & Accessories
Cooling Water System
Accessory Electric Plant
Instrumentation & Control
Improvements to Site
CO2 Capture System
Material Cost
Direct Labor
Indirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Fee
Contingency & Escalation$76.7M
Project Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$19.9M
Pre-production Cost
Inventory Capital
Total Capex$595.5M

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Balance of Plant (Boiler, cooling tower, multipurpose building and substation)
Earthwork Associated with Carbon Capture
Water Supply and Treatment
Wastewater
Drainage
Power Supply
Controls & Internet
Owner Facilities
Impurity Removal and CO2 conditioning
Enclosures & Buildings
Carbon Capture Plant
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B