Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
COโ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ concentration
6.0%mol%
โธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ
CO2 absorptionโ
Civil structural workโ
General utility systemโ
CO2 Compression Equipmentโ
Flue Gas Conditioningโ
Solvent regenerationโ
Stack connection and modificationโ
โธIndirect Field Costs$59.1M
Construction preliminariesโ
Engineeringโ
Mechanical completion, commissioning and testingโ
Trainingโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
CEMEX / Balcones Cement Plant
COโ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
โMW
COโ concentration
12.8%mol%
โธDirect Field Costs$575.3M
Absorber, cooling system, compression, vessels, pumpsโ
Piping materials, ductwork, racksโ
Civil materials, concrete, site materialsโ
Structural steel materialsโ
Electrical materials and equipmentโ
Instruments and automation hardwareโ
Insulation materialsโ
Paint and coatingsโ
Freight, heavy lift, haulingโ
All field installation laborโ
โธIndirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overheadโ
EPC engineering and detailed designโ
โธContingency & Escalation$145.5M
Contingencyโ
Escalationโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$23.6M
Owner's costโ
Total Capex$849.3M
Calpine / Deer Park Energy Center
COโ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
COโ concentration
5.2%vol%
โธDirect Field Costs$1.32B
CO2 Technologyโ
โธIndirect Field Costs$754.3M
Indirect Field Costsโ
โธContingency & Escalation$303.0M
Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$2.38B