Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
COโ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ concentration
6.0%mol%
โธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ
CO2 absorptionโ
Civil structural workโ
General utility systemโ
CO2 Compression Equipmentโ
Flue Gas Conditioningโ
Solvent regenerationโ
Stack connection and modificationโ
โธIndirect Field Costs$59.1M
Construction preliminariesโ
Engineeringโ
Mechanical completion, commissioning and testingโ
Trainingโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
(no name)
COโ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
โ
Parasitic load
โMW
COโ concentration
7.0%mol%
โธDirect Field Costs$520.0M
Report did not provide a further cost breakdown.
โธIndirect Field Costs$160.3M
Report did not provide a further cost breakdown.
โธContingency & Escalation$293.2M
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$973.6M
Calpine / Deer Park Energy Center
COโ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
COโ concentration
5.2%vol%
โธDirect Field Costs$415.7M
Feedwater & Miscellaneous Balance of Plant Systemsโ
Combustion Turbine & Accessoriesโ
HRSG, Ductwork, & Stackโ
Steam Turbine & Accessoriesโ
Cooling Water Systemโ
Accessory Electric Plantโ
Instrumentation & Controlโ
Improvements to Siteโ
CO2 Capture Systemโ
Material Costโ
Direct Laborโ
โธIndirect Field Costs$83.1M
Engineering, Construction Management, Home Office and Feeโ
โธContingency & Escalation$76.7M
Project Contingencyโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$19.9M
Pre-production Costโ
Inventory Capitalโ
Total Capex$595.5M