Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports โ tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
COโ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
COโ concentration
6.0%mol%
โธDirect Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary systemโ
CO2 absorptionโ
Civil structural workโ
General utility systemโ
CO2 Compression Equipmentโ
Flue Gas Conditioningโ
Solvent regenerationโ
Stack connection and modificationโ
โธIndirect Field Costs$59.1M
Construction preliminariesโ
Engineeringโ
Mechanical completion, commissioning and testingโ
Trainingโ
โธContingency & Escalationโ
Report did not provide a further cost breakdown.
โธInterest During Construction$27.0M
Report did not provide a further cost breakdown.
โธOwners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M
CLECO / Brame Energy Center Madison 3 Unit
CoalFEEDยท Cleco Powerยท 2025-03-25
COโ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
โMW
COโ concentration
14.1%vol%
โธDirect Field Costs$667.2M
Report did not provide a further cost breakdown.
โธIndirect Field Costs$509.3M
Report did not provide a further cost breakdown.
โธContingency & Escalation$120.7M
Report did not provide a further cost breakdown.
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Costโ
Report did not provide a further cost breakdown.
Total Capex$1.30B
Phillips 66 / Rodeo Refinery
COโ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
โMW
COโ concentration
18.0%vol%
โธDirect Field Costs$100.7M
Laborโ
Major Equipmentโ
Site Improvementsโ
Concreteโ
Structural Steelโ
Ductwork, Insulation, Pipingโ
Instrumentation and Electricalโ
Paintingโ
Freightโ
Design Allowanceโ
โธIndirect Field Costs$60.9M
Indirect Laborโ
Indirect Materialsโ
Engineeringโ
Project Development (FEL 2 and 3)โ
โธContingency & Escalation$48.3M
Contingencyโ
Escalationโ
โธInterest During Constructionโ
Report did not provide a further cost breakdown.
โธOwners Cost$29.4M
Report did not provide a further cost breakdown.
Total Capex$239.4M